Qual destes é um exemplo de risco de PROJETO?

Options (Reading Mode) Click to filter discussion →
  1. A. Um cálculo financeiro incorreto no módulo de faturamento
  2. B. Uma falha de segurança no componente de autenticação
  3. C. Atraso na entrega por falta de pessoal qualificado
  4. D. Lentidão do sistema sob carga elevada de usuários
Reveal answer

Correct answer: Atraso na entrega por falta de pessoal qualificado

Reference: https://www.istqb.org/wp-content/uploads/2024/11/ISTQB_CTFL_Syllabus_v4.0.1.pdf

02 — The Myelin Layer · Canonical Discussion

Where the exam tries to trick you — and how those who passed solved it.

0 Passed

contributed to this question

Answer Distractor Matrix Click an option to filter or open its dissection.
✦ Consolidated Synthesis (Wiki) rev. #1 (baseline) · CC BY-SA 4.0
Start synthesis for this question →

No community synthesis consolidated for this question yet. Below is the verifiable official starting point — if you passed the exam, open the option dissection.

Official Answer (C): Atraso na entrega por falta de pessoal qualificado